arrow_back View all case studies
Fluoride Removal Logistics · Icheon

Logistics-Center Fluoride Issue — RO System

3-stage pretreatment + RO resolved fluoride, hardness and particulates in one system.

A reverse-osmosis (RO) system was designed, fabricated and installed for a logistics center in Icheon, Gyeonggi. The source water exceeded the drinking-water standard for fluoride and also carried high particulate and hardness loads.

Diagnosis

  • Fluoride — above the drinking-water limit
  • Particulates — heavy
  • Hardness — high

Solution — 3-stage pretreatment + RO

Pretreatment was built in three stages — sediment, activated carbon and ion-exchange softening — followed by an RO unit custom-designed to the site and target quality.

RO installation at the logistics center
Custom-designed RO system — pretreatment and product-line layout

Installation & commissioning

Media/resin charging, electrical interlock between the main panel and pretreatment valves, level-switch integration and fail-safe drain piping; staged commissioning from pretreatment backwash through manual and automatic RO modes.

Completed RO system and product tank
Commissioned — SUS-framed RO skid, control panel and product tank

Result

Multiple quality factors resolved in one system, delivered turnkey from design to commissioning.

Diagnose your water today

Tell us your water problem and our experts will diagnose it for free and propose the optimal solution and quote.

Could it work at your site? Free consultation arrow_forward